Main, Greystone, Lees report: 2025-05

Submitted by Peter Tobin

Convent site geothermal drilling

The drilling for geo-thermal at the convent site started in early May. The approximately month-long delay from the schedule was due, according to site manager Morley Hoppner to a wait for regulatory approval.

The pipes are 1.5 inches in diameter and will go down 800 feet. Drilling will be completed in about 6 weeks.

BarBurrito

Domicile stated that Barburrito’s occupancy approval from the City arrived May 7 but no opening date was mentioned.

Madonna statue relocation

There’s no word when the Madonna statue will be relocated to Immaculata. John Dance is trying to get more information.

170 Lees staff mud management at MUP

Staff at 170 Lees have taken effective measures to reduce mud flowing down onto the MUP including the installation of an attractive bridge.